Once the mould design has been approved, a standard injection mould at Longterm Mold generally reaches the first sample stage within 20–35 days. Simple tooling may be ready in approximately 20–25 working days, whereas high-precision, double-shot, and overmolding projects commonly require 35–45 working days.
This schedule covers the main stages of tooling development, including mould engineering, CNC machining, component fitting, mould assembly, trial runs, dimensional verification, and sample approval. The actual lead time depends on the mould structure, number of cavities, material selection, tolerances, and inspection requirements.
The process starts with a detailed review of the approved product design. Engineers develop the mould structure, confirm parting lines, evaluate ejection and cooling, and determine whether a single-cavity or multi-cavity configuration is appropriate. Hot-runner systems can also be included when required by the application.
After the design is finalized, mould components are manufactured through precision machining and CNC processing. Material options listed for these tools include S50C, P20, 1.2738, H13, and 718H. Longterm Mold uses both 3-axis and 5-axis CNC machining systems to produce mould components and precision inserts.
Once the machined components are completed, the mould is assembled and installed for a trial run. The resulting samples are reviewed for dimensions, surface quality, mould performance, and overall conformity with the approved design. High-precision projects may also require CMM measurement and trials over multiple production cycles.
Quality control can include IQC incoming inspection, first article inspection, full dimensional measurement, 3D inspection, surface checks, mould running tests, and final inspection before shipment. For projects that proceed to mass production, sample approval and customer sign-off are completed before production begins.
The 20–35-day standard range is a planning reference rather than a fixed guarantee. A simple mould with uncomplicated geometry generally moves through design, machining, and trial testing faster. More demanding projects take longer because they may involve tighter tolerances, complex cores and slides, multiple materials, additional cavities, or specialized inspection procedures.
Double-shot and overmold tooling is typically placed in the 35–45 working day category. These moulds require more complex construction and process coordination, while CMM inspection, surface evaluation, and multi-cycle mould trials add further verification time.
Longterm Mold reports a five-person R&D engineering team experienced in mould structural design, precision CNC solutions, sample validation, and manufacturing process optimization. The team uses UG, SolidWorks, and AutoCAD throughout the development process.
Its project experience includes an electronic housing mould for an Italian manufacturer, a double-shot overmolding project for a French product brand, a home appliance mould for a US distributor, and an industrial plastic component mould for an Australian manufacturer. Customer feedback has highlighted dimensional accuracy, smooth part surfaces, stable trial samples, responsive technical support, and dependable delivery schedules.
The company is certified to ISO 9001:2015 under certificate number 02825Q12549R0S. The certification applies to the design, manufacture, and sales of precision moulds, as well as the sale of plastic products.
| Tooling or production project | Typical time to sample-related completion | Typical inspection and trial work |
|---|---|---|
| Custom precision plastic injection mould | 20–35 days | IQC incoming inspection, mould trial, dimensional inspection, and final inspection before shipment |
| Simple custom mould with injection moulding | 20–25 working days | First article inspection, complete dimension measurement, and mould running test |
| OEM custom plastic injection mould | 25–35 working days | 3D inspection, dimensional verification, mould trial, and sample confirmation |
| High-precision, double-shot, or overmold tooling | 35–45 working days for complex moulds | CMM measurement, surface inspection, and multi-cycle mould trials |
| Mould development followed by mass production | Mould: 25–35 days; mass production: 7–15 days after sample approval | IQC, IPQC, FQC, and approved sample sign-off before shipment |
What is the usual lead time for a standard injection mould?
For a design-approved standard project, the normal planning range is 20–35 days. The final schedule depends on the tool design, cavity quantity, steel or mould material, tolerance requirements, and inspection plan.
Why do double-shot and overmold tools need more time?
These tools involve more complicated mould structures and process requirements. They are generally scheduled for 35–45 working days and may include CMM measurement, surface checks, and trials across multiple moulding cycles.
What is done after the first samples are moulded?
First samples are checked against the approved design through dimensional inspection, surface evaluation, and mould performance testing. If mass production is included, production normally starts 7–15 days after sample approval and sign-off.
For most design-approved injection mould projects, planning for 20–35 days is appropriate. Allow around 20–25 working days for a simple tool and 35–45 working days for complex precision, double-shot, or overmolding tooling. Longterm Mold provides OEM mould manufacturing, custom moulding with injection production, and complete tooling-to-production services.
The company lists a capacity of approximately 15–20 injection moulds per month and supports small- to medium-volume orders. For a project-specific quotation, tooling review, or technical consultation, contact rogerluo@longterm-mold.com.
Longterm Manufacturing Solutions Limited, operating as Longterm Mold, was established in 2010. The company supplies mould design, tooling, precision machining, mould manufacturing, and plastic parts production for customers in North America, Europe, and Australia.
With 50 employees, the manufacturer produces more than 300 moulds annually, with about 80% supplied to European and North American markets. Its ISO 9001:2015 certification covers precision mould design, manufacturing, sales, and the sale of plastic products. The company has served customers in electronics, appliances, automotive, industrial equipment, and consumer goods sectors.

REPORT